Colossus Supercomputer
Memphis, Tennessee, USA
xAI's Memphis AI supercomputer: the company says 100,000 H100s went live in 122 days; its gas turbines drew a Clean Air Act fight.
Key facts
- Location
- Paul R. Lowry Road, Memphis, Tennessee (Pidgeon Industrial Park)
- Operator
- xAI (X.AI Corp.), part of SpaceX since the "xAI Merger" effective 2 February 2026; reported in SpaceX's SEC filings among the "SpaceXAI entities"
- Building
- Former Electrolux manufacturing facility
- Build timeline
- Construction began 24 April 2024; 100,000 H100s online 2 September 2024 (Epoch AI estimate)
- First cluster
- About 100,000 H100s and about 130 MW, online in 122 days (company claim)
- Expansion
- Doubled to 200,000 GPUs in 92 days, by February 2025 (xAI claim; the same page also shows 180K GPUs)
- Power
- Supplied via MLGW; TVA board approved an additional 150 MW of firm power for xAI, contingent on contractual, financial and operational requirements (WSMV, Feb 2026)
- Uses
- Trained Grok models (Nvidia, Oct 2024); Anthropic agreed in May 2026 to use all of Colossus 1's capacity (Anthropic, 6 May 2026); SpaceX said in June 2026 that Grok-5 was being trained at Colossus II
Colossus is xAI's flagship AI data center on Paul R. Lowry Road in Memphis, Tennessee, housed in a former Electrolux factory. It was used to train xAI's Grok models (Nvidia, October 2024); since May 2026 Anthropic has had an agreement to use all of its compute capacity. SpaceX, whose filings report xAI since a merger effective February 2026, says the first cluster of about 100,000 Nvidia H100 processors came online in 122 days. The site has drawn opposition over unpermitted gas turbines, including a 2025 NAACP notice of intent to sue and an appeal against a 15-turbine permit, which was dismissed as moot in December 2025.
Highlights
- About 100,000 H100s online in 122 days (company claim)
- Housed in a former Electrolux factory in Memphis
- Trained Grok models from 2024; capacity leased to Anthropic since May 2026
- 15-turbine permit (July 2025); appeal dismissed Dec 2025
What Colossus is
SpaceX's June 2026 IPO prospectus defines COLOSSUS as its "flagship data center, located on Paul R. Lowry Road in Memphis, Tennessee", and COLOSSUS II as its data centers in Memphis and in Southaven, Mississippi. A fact sheet from the Memphis utility MLGW says xAI occupies the former Electrolux manufacturing facility in the Pidgeon Industrial Park. Nvidia said in October 2024 that Colossus was being used to train xAI's Grok family of large language models. On 6 May 2026 Anthropic said it had signed an agreement with SpaceX to use all of the compute capacity at Colossus 1, more than 300 megawatts and over 220,000 Nvidia GPUs. As of SpaceX's June 2026 prospectus, the May 2026 cloud-services agreements with Anthropic covered approximately 325,000 Nvidia GPUs across Colossus and Colossus II; after an initial three-month period either party may terminate them on 90 days' notice. The same prospectus said Grok-5 was then being trained at Colossus II. SpaceX says Colossus and Colossus II together provide approximately 1.0 gigawatt of compute power. Independent tracker Epoch AI, which lists Colossus 1 as used by Anthropic, estimated in June 2026 that it hosts about 276,000 H100-equivalents of compute on 340 MW of IT power, at a capital cost of $12.9 billion.
How fast was it built?
The 122-day figure is a company claim. Nvidia's October 2024 release said the facility and supercomputer were "built by xAI and NVIDIA in just 122 days", with 19 days from the first rack to training, and quoted Musk calling Colossus "the most powerful training system in the world". SpaceX's prospectus repeats that the first cluster of approximately 100,000 H100 processors, about 130 megawatts, came online in 122 days in the shell of an existing factory. Epoch AI, which tracks data centers using satellite imagery, dates the start of construction to 24 April 2024 and puts 100,000 H100s online on 2 September 2024, at about 139 MW of IT power. xAI's own Colossus page says it then doubled the system to 200,000 GPUs in 92 days, and counts 276 days from groundbreaking in May 2024 to February 2025. The same page also shows a figure of 180K H100 GPUs in a single interconnected cluster.
Power and jobs
An undated MLGW fact sheet (filed under 2024) says xAI's initial substation would be raised to 50 MW and that xAI requested an additional 100 MW, for a total of 150 MW. The fact sheet made that conditional on Tennessee Valley Authority board approval, enrolment in a demand-response program, a $1.7 million line upgrade and a new substation. MLGW forecast that the project would create about 300 or more new jobs. In February 2026 WSMV reported that the TVA board had unanimously approved a power increase for xAI, under which xAI would receive an additional 150 megawatts of firm power. WSMV said the approval was contingent on xAI meeting key contractual, financial and operational requirements.
Gas turbines and the Memphis permit
In June 2025 the Southern Environmental Law Center (SELC), on behalf of the NAACP, sent xAI a letter signaling their intent to sue under the Clean Air Act over the company's continued use of unpermitted gas turbines at its data center in South Memphis. SELC said aerial images showed 35 turbines at the site in March 2025. On 2 July 2025 the Shelby County Health Department issued a permit authorizing xAI to construct and operate 15 natural gas turbines. SELC, on behalf of the NAACP and Young, Gifted and Green, appealed to the Memphis and Shelby County Air Pollution Control Board, saying the decision "failed to address the dozens of unpermitted gas turbines that were installed at the xAI data center over the last year". xAI called the appeal baseless and said the 15 permanent turbines "would make the Electrolux facility the lowest emitting facility of its type in the United States." On 15 December 2025 the board dismissed the appeal 6-1 on the grounds of mootness.
Colossus II and the Southaven lawsuit
A separate federal case concerns Colossus II. On 14 April 2026 the NAACP sued X.AI Corp. and MZX Tech, LLC in the US District Court for the Northern District of Mississippi over gas turbines in Southaven, Mississippi, that power Colossus II; Earthjustice said xAI was operating 27 gas turbines there without an air permit. SpaceX's prospectus lists lawsuits over unpermitted turbines at Southaven as a risk factor. In June 2026 the Justice Department moved to intervene and dismiss the case, arguing it threatened "national, economic, and energy security". According to SpaceX's October 2026 quarterly report, on 19 October 2026 the court granted the United States' motion to intervene but declined to allow it to dismiss the case. xAI said in July 2026 that, under an agreed order with Mississippi regulators, all 69 temporary turbines at Southaven would be removed by July 2027, and that a 1.2 GW permanent plant of 41 turbines, permitted in March 2026, was under construction. Earthjustice's April 2026 announcement of the lawsuit counted 27 turbines; xAI's July 2026 page refers to 69 temporary turbines at Southaven. On 30 October 2026 the court also denied xAI's motion to dismiss the lawsuit; according to Earthjustice, the NAACP's motion for a preliminary injunction was still awaiting a ruling.
Sources
- SEC — SpaceX prospectus (Form 424B4), June 2026
- SEC — SpaceX quarterly report (Form 10-Q) for the quarter ended 30 September 2026
- Nvidia — Spectrum-X Ethernet networking and xAI Colossus (October 2024)
- xAI — Colossus
- xAI — Memphis updates (July 2026)
- Epoch AI — Colossus 1 (AI data centers directory)
- Anthropic — announcement of agreement to use SpaceX’s Colossus 1 compute (6 May 2026)
- MLGW — xAI and MLGW Quick Facts (undated; filed under 2024)
- WSMV — TVA approves power increase for xAI
- NAACP — Elon Musk's xAI threatened with lawsuit over air pollution from Memphis data center
- Tri-State Defender — Shelby County approves xAI air permit amid lingering community opposition
- Data Center Dynamics — Campaigners appeal decision to permit gas turbines at xAI's Memphis data center
- Memphis Flyer — xAI permit appeal dismissed (December 2025)
- Action News 5 (WMC) — Shelby County Air Pollution Control Board denies appeal over xAI turbine use, citing mootness
- Earthjustice — xAI sued for illegal power plant (April 2026)
- Earthjustice — Court denies xAI's motion to dismiss air pollution lawsuit (30 October 2026)
- Al Jazeera — Trump administration seeks to halt air pollution lawsuit against xAI data center
Frequently asked
Cite this page
Reviewed Nov 12, 2026ElonFacts.org. (2026). Colossus Supercomputer. Retrieved from https://elonfacts.org/facilities/colossus-memphis
"Colossus Supercomputer." ElonFacts.org, Nov 12, 2026, https://elonfacts.org/facilities/colossus-memphis.
@misc{elonfacts-facilities-colossus-memphis, title={Colossus Supercomputer}, author={{ElonFacts.org}}, year={2026}, url={https://elonfacts.org/facilities/colossus-memphis}}
https://elonfacts.org/facilities/colossus-memphis